Hatteras Power Blackout-Northern Beaches Unaffected

Digging for the severed cable at the south end of the Bonner Bridge construction zone. Photo, Outer Banks Voice. Digging for the severed cable at the south end of the Bonner Bridge construction zone. Photo, Outer Banks Voice.

The news just came out a little while ago, that Hatteras Island is being evacuated. This is a manmade catastrophe, and has nothing whatsoever to do with Mother Nature.

What Happened?

Early yesterday morning, PCL Construction who is building the new Bonner Bridge, was pounding a piling into the south end of Oregon Inlet.

When they cut through a power cable carrying electricity to Hatteras Island and Ocracoke the effect was immediate. All power south of Oregon Inlet was immediately lost.

Joe Lamb Jr., & Associates visitors, please note—this does not effect anything from Nags Head north, where our Joe Lamb Jr., & Associates properties are located.

But the effect on our friends on Hatteras Island and Ocracoke is dramatic and difficult to witness.

Although there are emergency generators on hand, and more are coming, they are designed to handle emergency power loads only. The generators cannot handle air conditioning and residents have been told to expect rolling blackouts.

Evacuations Ordered

Hyde County ordered Ocracoke evacuated yesterday, Thursday, and Dare County ordered Hatteras Island evacuated today. Governor Roy Cooper has declared a state of emergency, allowing some weight restrictions to be lifted on trucks to more efficiently move supplies and more generators.

There is considerable uncertainty about how long repairs will take. Cape Hatteras Electric Coop (CHEC) who manages the power grid on Hatters Island put out a statement saying,  "CHEC is working to assess the extent of the damage and plan for the repair. Assuming that the cooperative has the materials on hand, repairs could take several days to complete. If materials are not available locally, repairs could take weeks."

The latest information is the original contractor who laid the power cable is on hand and PCL is working to excavate the site and inspect the cable.